BENETA WELL NO.2
PROJECT:
BENETA WELL NO. 2 – PHASE II EQUIPPING PROJECT.
CIP NO. 60151
.​
LOCATION:
18001 BENETA WAY, TUSTIN, CA 92780.
OWNER:
City of Tustin.
​
WORK DESCRIPTION:
Demolition of existing site improvements; new 1500 gpm, 300 hp VFD operated well pump, 12 inch discharge piping, and connections to the City’s existing water distribution system; new 420 sf and 215 sf masonry buildings; bulk sodium hypochlorite storage and disinfection system; construction of 90 LF of 18 inch rcp drain pipe and outlet structure to an existing drainage channel; new 600 amp electrical service, switchboard and motor control center; plc based well control panel including SCADA integration; 8 foot high masonry perimeter walls with motorized gate; AC yard paving; curb, gutter, sidewalk, and driveway replacement; and landscaping and irrigation system improvements.
PROJECT COMPLETION DATE:
June 2025.
​
IMAGE GALLERY: ​​​​
​​​​​​
​